Page 31 - Customize-Project-Plan-by-tailoring-Smartsheet
P. 31

Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


                                 o  We need to perform a "Feasibility Study" to define, which material, which
                                     equipment and which work steps and effort will be necessary to manufacture
                                     the product later.

                                    Special demand: Since we are certified according to IATF 16949, the partici-
                                    pants  of  the  cross-functional  team  who  will  perform  the  Feasibility  Study
                                    should also "sign and confirm" it.

                                 o  Based on the Feasibility Study, a "Cost Estimate" will be created to determine
                                     the selling price.

                                 o  Our customer demands in their RFQ (Request for Quotation) a mandatory
                                     "Due Date" because they would like to present the parts at a trade fair.

                                 o  Then we send our quotation and expect from the customer their "Purchasing
                                     Order".


                            Then the Project Phase begins:

                                 o  Project "Kick-Off" and introducing the project team members.

                                 o  "Designing" the parts.

                                 o  "Material procurement", concerning in-house as well purchasing from suppli-
                                     ers.

                            Part Number    Part Name DE        Part Name EN       Lead Time   Supplier


                            P1001.01.00    Oberteil            Upper Housing      2 weeks     In-house

                            P1001.02.00    Unterteil           Bottom Housing     2 weeks     In-house

                            P1001.03.00    Leiterplatte        Conductor Board    4 weeks     HAP Power

                            P1001.04.00    Vordere Abdeckung   Front Cap          2 weeks     In-house

                            P1001.05.00    Hintere Abdeckung   Hind Cap           2 weeks     In-house




                                 o  Manufacturing and "Assembly" of the parts.

                                 o  An  "Alternating  Climate  Test"  according  to  our  Design  Verification  Plan
                                     (DVP/R) through 8 consecutive days.

                                 o  "Shipping" the parts to the customer.

                             Task: Let's plan and monitor the project successfully!