Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


               56. Roll-up Sheet



                   56.1.     Roll-up Sheet

               A Roll-up is some kind of simple summary, where some data from some different sheets gets accu-
               mulated in a sheet that can be used later to supply information mainly to a dashboard.

               The Roll-up is often integrated into the same sheet that is supposed to be evaluated, but for the sake
               of clarity it should be kept on a separate sheet. Our target here in this Roll-up is to figure out how
               many hours have already accumulated in the project concerning some departments. Maybe you still
               recall that we added once a column that was called "Net Duration Hours" when we talked about Du-
               rations and Resource Management?






























               How can we figure this out?

               First, we create a new sheet, just a grid. We just call it "Roll-Up".