Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


               17. Dependencies (Predecessors)




                     In order to make the individual tasks (work packages, rows, ...) dependent on one another, a
                      reference is now made to the row number(s) through a so-called "Predecessor".

                     The question often arises whether to refer to a summary process (parent) or to the last row of
                      such a block either. My recommendation is that you reference to the summary process ("par-
                      ent"), because the block may not be structured chronologically, and it is easy to overlook a
                      task that may take longer than the last one.





















                     You can also address several row numbers, but then they need to be separated by a comma.

















                                                                         ,