Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


                      23.1.1.       Forward Pass

                     The Forward Pass is recommended, otherwise you rob yourself of possible "buffer time". This
                      "buffer time" is called in project management "slack time".

                     Forward planning is the default in Smartsheet (and by the way, in Microsoft Project  as well).
                                                                                                 

                     Forward Pass Planning: All tasks begin as early as possible.

                     Caution: Please only enter the first (1st) date (the start date); because all other dates will be
                      then later calculated by using "Dependencies" / "Predecessors" and "Durations", which will
                      make the schedule of the project plan "swim / float" more or less forward into the future.

                     Watch the little arrows in the GANTT-chart to recognize at a glance the pass direction.

                     Important: The milestone of row 8, pictured in the screenshot here, is a "Solid Milestone" (see
                      about "Solid Milestone", at chapter "18.1 Milestones", page 52).

                                                                                              Finish
                                                                Today














                                                                        Start


                                                                                                Due Date





                                                   TODAY   DUE DATE







               More information on the internet:


               https://monday.com/blog/project-management/forward-pass-project-management