Customize your Project Plan
                                                                                                            
                                                                               by tailoring Smartsheet


                      23.1.2.       Backward Pass


                      • Backward Pass Planning is not recommended, otherwise you rob yourself of slack time in
                      advance.

                      • However, you should be familiar with backward planning, since you may also encounter such
                      a project plan from somebody else.

                      • Backward Pass Planning: All tasks start as late as possible.

                      • To perform Backward Planning we add to the predecessor number the term "SF", which
                      stands for "Start-Finish". By the way, we already talked about in "17.1 Dependencies (Prede-
                      cessors)" page 91.

                      • Watch the little arrows in the GANTT-chart to recognize at a glance the pass direction.